Hi
I have a question about planning a job in Backup Exec 2012.
My Infrastructure:
- Backup Exec 2012
- 1 Overland Tape Library with 2 tape drives
- Only Windows
Every 4 weeks, we will bring our tapes in a safe and change the tape drive. These bands are called "Monthly".
We usually do a full save every Friday and an increment job from Monday to Thursday on tapes 1-21 into a Overland Library. Saturday and Sunday are no jobs configured. We want to configure that all 4 weeks the Monthlyjob is the only one who is running and not even the full save additional. This monthly save goes to the tapes 22-28.
The rhythm looks:
- Week 1 Full
- Week 2 Full
- Week 3 Full
- Week 4 Month
- Week 5 Full
- Week 6 Full
- Week 7 Full
- Week 8 Month
- Week 9 Full
- and so on..
There was an option in Backup Exec 2010 calendar but they skipped that out.
How can I do this with Backup Exec 2012 Version?. Has anyone an idea?